| 20251125 |
Orange County |
Stanton |
City Council |
Order of Business 9 |
9P.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
APPROVING SUBDIVISION PARCEL MAP NO. 2022-152
The subdivision parcel map for the development of four detached single-family dwelling
units located at 7082 Kermore Lane has been submitted by the developer for final
certification and recordation.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 3, Section 15303 (New Construction or Conversion
of Small Structures); and
2. Adopt Resolution No. 2025-36 approving final Parcel Map No. 2022-152, entitled:
“A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF STANTON,
CALIFORNIA, APPROVING SUBDIVISION PARCEL MAP NO. 2022-152 FOR
THE PROPERTY LOCATED AT 7082 KERMORE LANE”; and
3. Find that the recordation of Parcel Map No. 2022-152 will not be in violation of any of
the provisions of Section 66474, 66474.1, and 66474.2 of the Subdivision Map Act;
and
4. Find that the proposed subdivision, together with the provisions for its design and
improvement, is consistent with the general plan required by Article 5 (commencing
with Section 65300) of Chapter 3 of Division 1 of the Government Code, or any specific
plan adopted pursuant to Article 8 (commencing with Section 65450) of Chapter 3 of
Division 1 of the Government Code; and
5. Authorize the Mayor to execute the Subdivision Improvement Agreement for Parcel
Map No. 2022-152; and
6. Direct the City Engineer to review and approve any further technical edits necessary
to allow for County Surveyor approval and for recordation of the map with the County
Recorder of Orange County, and if edits are necessary, to require a revised Parcel
Map; and
7. Direct the City Clerk to endorse on the face of the map of the Parcel Map, the
certificate which embodies the approval of said map, and submit the map to the
County Recorder of Orange County for recording.
END OF CONSENT CALENDAR |
November 25, 2025
Orange County
Stanton
City Council
Order of Business 9
#P
|
| 20251125 |
Orange County |
Stanton |
City Council |
Order of Business 9 |
9N.
APPROVAL OF FIRST AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
WITH CSG CONSULTANTS, INC. TO PROVIDE ON CALL SERVICES RELATED TO
BUILDING AND SAFETY SERVICES
At its meeting of November 8, 2022, the City Council awarded a contract to CSG
Consultants, Inc. to provide on-call building and plan check services. The three-year
contract, expiring on December 30, 2025, provides for two optional one-year extensions.
The proposed First Amendment presented for the Council’s consideration exercises the
first of the one-year extensions, extending the term of the Agreement to December 30,
2026, and increases the compensation based on consultant’s adjusted rates under
Section 3.3.1 of the amended Agreement.
RECOMMENDED ACTION:
1. City Council find that the recommended actions are exempt from CEQA per
Section15378(b)(5) which excludes organizational or administrative activities of
governments that will not result in direct or indirect physical changes in the
environment; and
2. Approve the First Amendment to the Professional Services Agreement with CSG
Consultants, Inc. and allow the City Attorney to make minor edits as necessary prior
to the execution of the Amendment; and
3. Authorize the City Manager to execute the First Amendment to the Professional
Services Agreement with CSG Consultants, Inc. |
November 25, 2025
Orange County
Stanton
City Council
Order of Business 9
#N
|
| 20251125 |
Orange County |
Stanton |
City Council |
Order of Business 9 |
9K.
AWARD OF CONSTRUCTION CONTRACT FOR THE STANTON CENTRAL PARK
TENNIS COURTS RENOVATION PROJECT (TASK CODE NO. 2025-202) AND
APPROVAL OF THE FIRST AMENDMENT TO THE PROFESSIONAL SERVICES
AGREEMENT WITH RHA LANDSCAPE ARCHITECT-PLANNERS, INC.
Five bids for the Stanton Central Park Tennis Courts Renovation Project were opened on
September 30, 2025. Based on the post-bid analysis of the bids received, staff has
determined the bid submitted by A2Z Construct, Inc. to be the lowest responsible and
responsive bid at $380,100.00. To ensure construction of the Project is in conformance
with the design, staff is recommending approval of a First Amendment to RHA Landscape
Architects-Planners, Inc’s Agreement to extend the term of the Agreement and increase
scope of work.
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 1, Section 15301(a) as operation, repair, and minor interior or
exterior alterations of existing public facilities; and
2. Award a construction contract for the Stanton Central Park Tennis Courts Renovation
Project to A2Z Construct, Inc. for the bid amount of $380,100.00 and reject all other
bids; and
3. Authorize the City Manager to bind the City of Stanton and A2Z Construct, Inc. in a
contract for the construction; and
4. Authorize the City Manager to approve contract change orders, not to exceed
$38,010.00; and
5. Approve the First Amendment to the existing Agreement with RHA Landscape
Architect-Planners, Inc. and allow the City Attorney to make minor edits as necessary
prior to the execution of the Amendment; and
6. Authorize the City Manager to execute the First Amendment to the existing Agreement
with RHA Landscape Architect-Planners, Inc. |
November 25, 2025
Orange County
Stanton
City Council
Order of Business 9
#K
|
| 20251125 |
Orange County |
Stanton |
City Council |
Order of Business 9 |
9J.
AWARD A PROFESSIONAL SERVICES AGREEMENT TO MATRIX CONSULTING
GROUP FOR A COMPREHENSIVE DEVELOPMENT IMPACT FEE NEXUS STUDY
The City seeks a firm to prepare a Comprehensive Development Impact Fee Nexus Study
based on the proposed infrastructure requirements to support the City's General Plan
growth projections. After completion of a competitive procurement process, staff
recommends awarding a contract to Matrix Consulting Group for $32,500.
RECOMMENDED ACTION:
1. City Council declare this project to be categorically exempt under the California
Environmental Quality Act, Section 15378(b)(5) – Organizational or administrative
activities of governments that will not result in direct or indirect physical change in the
environment; and
2. Award a professional services agreement to Matrix Consulting Group for a
Comprehensive Development Impact Fee Nexus Study in the amount of $32,500; and
3. Authorize the City Manager to bind the City of Stanton and Matrix Consulting Group
in an Agreement to provide the services; and
4. Authorize the City Manager to approve a contingency in the amount of $3,250 to Matrix
Consulting Group. |
November 25, 2025
Orange County
Stanton
City Council
Order of Business 9
#J
|